£158m redress agreed for two-year delay to ‘Western Link’ subsea cable

0
654

National Grid Electricity Transmission plc (NGET) and Scottish Power Transmission plc (SPT) have agreed to pay a redress package of £158 million for delays to the Western Link Project, following an Ofgem investigation.

£15 million of the redress package will be paid into Ofgem’s Redress Fund. Operated by the Energy Saving Trust, the Fund allows companies to pay a sum of money to appropriate charities, trusts, organisations or consumers as a result of breaches of licence conditions.

According to Ofgem, the remainder of the redress package will be returned via reduced system charges. These charges are ultimately paid for by consumers as part of their overall electricity bills, so consumers will benefit from this redress package through lower bills.

The regulator recognises that consumers have benefited by a further £100 million because of the companies’ financial management of the project and their contract management strategy. Ofgem’s network price control ensures this is returned to customers through lower system charges.

Western Link is a transmission project worth around £1.2 billion, providing a major subsea electricity link between Scotland and Wales. The link was designed to transport electricity, often from green sources like offshore wind, between Scotland and Wales.

It provides an additional 2,250MW of capacity, equivalent to powering over two million homes, and is crucial to helping Britain reach its targets of net zero greenhouse gas emissions.

The two-year delay restricted renewable generators in Scotland exporting electricity to England and Wales, because at times there was not enough capacity to do so.

Because renewable generators in Scotland were unable to transport the energy they were generating, National Grid ESO would have sometimes had to reduce the output from windfarm generators to protect the electricity system. This ultimately led to higher costs for consumers.

NGET and SPT own the licence for the project and contracted with a contractor to deliver it. The link fell two years behind its expected delivery date of March 2017 to June 2019.

Ofgem’s investigation found that the root causes of the delay were problems with manufacturing processes, installing the cables and commissioning tests. It acknowledged that NGET and SPT did not cause or exacerbate the delay.

Ofgem holds NGET and SPT ultimately responsible, as licence holders, for the delay caused by their supply chain.

Cathryn Scott, Ofgem’s Director of Enforcement and Emerging Issues, commented on the announcement:  “To deliver the UK’s climate change ambitions, more of our electricity will come from renewable generation. This is already happening, with offshore wind and other projects in development.

“Innovative projects such as the Western Link are vital in moving clean energy from where it’s produced to where it’s needed.

“However, they must be delivered on time and to the standards agreed. Where they are not, as the energy regulator, we will hold the licensees accountable.”

More information about this decision is available on the Ofgem website.